CFE and MEXDC Agree on Joint Planning for 1.73 GW of Data Center Capacity

CFE and MEXDC are coordinating electrical grid planning to meet projected data center demand of 1.73 GW by 2031, up from 279 MW of installed capacity today and 205 MW under construction in 2026.

Por REDACCIÓN THE WATT · 12 sep 2026 · 2 MIN READ
Power transmission towers leading to an industrial data center in Mexico
Imagen generada con inteligencia artificial

Mexico's federal utility CFE (Comisión Federal de Electricidad) and the Mexican Data Center Association (MEXDC) reached a coordination framework on September 10, 2026, designed to anticipate the sector's power demand, which the industry projects at 1.73 GW by 2031, up from 279 MW of installed capacity and 205 MW currently under construction.

Under the agreement, as reported by La Jornada, MEXDC will provide CFE with consolidated data on future projects, expansion outlooks, and consumption profiles. CFE's technical teams will use that information to design the generation, transmission, distribution, and storage solutions each project requires based on its location. BNamericas' regional coverage identifies grid connection speed and reliability as the top barrier cited by sector investors. Mexico is Latin America's largest data center destination and the landing point for U.S. computing demand seeking local installed capacity, making grid planning a precondition for investment.

The agreement includes weekly technical working groups to review data, statistics, and growth projections, and to track projects requiring new capacity. It also covers follow-through on regulatory processes managed by the National Energy Control Center (CENACE), the operator of the National Electric System (SEN), and the identification of Distribution personnel responsible for each zone where data centers already operate. CFE maintains that the country has sufficient generating capacity to support sectoral growth, provided infrastructure planning is done in advance, as reported by La Jornada. The gap between the 279 MW currently operational and the projected 1.73 GW means multiplying sector capacity more than sixfold in under six years, with 205 MW already under construction in 2026.

The first metric to watch will be the load projections coming out of the weekly working groups and their translation into transmission and storage projects. Where that infrastructure lands will determine which data center projects can connect, and on what timeline.

This article was written with artificial intelligence assistance based on verified sources and reviewed by a human editor before publication.

This article was drafted with AI assistance from verified sources and reviewed by a human editor before publication.

Frequently asked questions

¿Cuánta electricidad requerirán los data centers en México?
La industria proyecta 1.73 GW de capacidad requerida hacia 2031, desde 279 MW instalados y 205 MW en construcción durante 2026, según las cifras difundidas por la CFE y la MEXDC el 10 de septiembre de 2026.
¿Qué acordaron la CFE y la MEXDC?
Un esquema de coordinación en el que la MEXDC comparte con la CFE información consolidada de proyectos y perfiles de consumo, con mesas técnicas semanales, atención territorial por zona y seguimiento de trámites ante el CENACE.
¿Qué sigue en la planeación eléctrica para data centers?
Las mesas técnicas semanales definirán las proyecciones de carga y las obras de generación, transmisión, distribución y almacenamiento que cada proyecto requiere según su ubicación.