Pertamina kicks off basic engineering for Lumut Balai 3, a 55 MW geothermal plant in Sumatra

The Amythas and ELC Electroconsult consortium has six months to design the third geothermal unit, with commercial operation targeted for 2030.

By THE WATT NEWSROOM · Nov 24, 2026 · 2 MIN READ
View of the Lumut Balai 3 geothermal plant with steam pipes in Sumatra
AI-generated image

PT Pertamina Geothermal Energy (PGEO) completed the initial front-end engineering design (FEED) stage for Lumut Balai Unit 3, a 55 MW geothermal plant in Sumatra, Indonesia, on November 2, 2026. The FEED contract went to a consortium made up of PT Amythas and ELC Electroconsult, with an expected timeline of six months, according to ThinkGeoEnergy.

The scope covers the design of the geothermal fluid gathering and reinjection system and of the plant itself, plus the prequalification and tender documents for contracting the construction work. ELC Electroconsult had already prepared the FEED for units 1 and 2, a relationship with PGEO that ran from 2011 to 2025. Those two units total 110 MW: unit 1 has been operating since 2019 and unit 2 since 2025, according to detikFinance, so with the third the complex will reach 165 MW. For Mexico, whose geothermal capacity is concentrated in Cerro Prieto, Los Azufres and Los Humeros, the case shows the sequence through which leading markets mature a conventional project: design, drilling and construction tendering, with long-term financing closed before building begins.

The physical work is advancing in parallel. Drilling of the first well began in July 2026 and initial infrastructure work on Cluster 4 started on November 6, according to detikFinance. That package includes access roads and piping for drilling water, according to ThinkGeoEnergy. The commercial operation target is 2030, though PGEO is looking to bring it forward. Edwil Suzandi, PGEO's director of Exploration and Development, told CNBC Indonesia that the company is aiming for 2029 and, at the latest, 2030, with the EPCC contract (engineering, procurement, construction and commissioning) expected in 2027 and at least 30 months of construction. The project has 158.86 million dollars in financing from the Japan International Cooperation Agency (JICA), within a broader PGEO package, according to ThinkGeoEnergy.

What comes next is the close of the FEED and the EPCC tender in 2027, two milestones that define the timeline toward commercial operation between 2029 and 2030. For geothermal in the region, the Lumut Balai 3 schedule sets the benchmark for how long a conventional unit takes from design to dispatch.

This article was drafted with the assistance of artificial intelligence from verified sources and reviewed by a human editor before publication.

This article was drafted with AI assistance from verified sources and reviewed by a human editor before publication.