Spain requires hourly 80% renewable backing for data centers from 10 MW
Spain requires data centers of 10 MW or more to certify 80% renewables hour by hour from November 22; it sets water limits and compensation payments.

Data centers connecting to the Spanish electricity grid with 10 megawatts (MW) of access capacity or more must certify that 80% of their consumption in each hour comes from renewable generation produced in that same hour. Royal Decree 1032/2026, published in the Official State Gazette on November 21 and in force from the 22nd, also applies to facilities of the same owner at a single site whose combined capacity exceeds that threshold.
The rule arrives with capacity already committed. In the prior presentation, Vice President Sara Aagesen put the access permits already granted to data centers at 15 gigawatts (GW) and the applications in the queue at another 20 GW, according to La Razón. The hourly correlation criterion replaces the practice of offsetting annual consumption with certificates: a purchase covering 12 months can leave gaps in nighttime hours, and the decree allows self-consumption, power purchase agreements (PPAs) and storage to close them. The design adds to a regulatory debate already under way in the United States, where, according to Latitude Media, transmission-owning companies asked FERC, the federal energy regulator, to require long-term contracts from data centers before building grid reinforcements.
The decree also sets efficiency requirements. Until the European labeling scheme expected in August 2027 applies, facilities must meet a PUE (power usage effectiveness) of 1.25 or less and a WUE (water usage effectiveness) of 0.1 or less, with annual verification. On additionality, the associated generation must have come online no more than 36 months before the data center enters operation, with exceptions for solar PV, repowering and plants at the end of their regulatory life. Deviations are offset with monthly payments ranging from 2 to 16 euros per megawatt hour (MWh) depending on the size of the hourly shortfall, and from 6 to 25 euros per MWh depending on the additional generation deficit. Permits already granted but not yet connected have six months to certify the requirements.
The next checkpoint in Spain is the review of the 20 GW of queued applications and the biennial assessment by the National Commission on Markets and Competition (CNMC). In the United States, comments on the contract proposals before FERC close on December 7.
This article was drafted with the assistance of artificial intelligence from verified sources and reviewed by a human editor before publication.
Sources
- Real Decreto 1032/2026, de 20 de noviembre, por el que se regula el acceso a la red de los centros de datos
- España exige desde hoy a los nuevos grandes centros de datos que respalden el 80% de su consumo con energía renovable generada en esa misma hora
- Utilities want FERC to lock data centers into paying for grid upgrades
Related stories
This article was drafted with AI assistance from verified sources and reviewed by a human editor before publication.