Power availability now decides where Mexico's $82 billion in data centers lands

Power availability now determines where data centers are built in Mexico: MEXDC projects $82 billion by 2031, and the grid sets the pace.

By THE WATT NEWSROOM · Nov 25, 2026 · 2 MIN READ
Electrical transmission towers next to industrial data center buildings in Mexico
AI-generated image

The availability of electrical power is now the first criterion for siting a data center in Mexico, a market projecting 82,000 million dollars of direct and indirect investment toward 2031, according to the Mexican Data Center Association (MEXDC), in figures presented at a panel reported by Global Energy on November 24, 2026.

Of that amount, roughly 20,500 million dollars correspond to construction of facilities and the rest to the supply and services the infrastructure requires. Mexico operates 484 megawatts (MW) of installed capacity, against 1.4 gigawatts (GW) in Brazil, and the industry calculates that each MW commits close to 10 million dollars of investment. About 70% of the country's data centers are concentrated in Querétaro, where the announced projects imply multiplying state electricity demand by more than six toward 2031, according to Bloomberg Línea. The panel takes place at a moment when digital infrastructure projects are stalled in the United States.

Connection timelines show where the chain stops. Obtaining an electrical connection contract takes at least eight months and stretches to three years with reviews, and a single project in Querétaro has required around 111 permits unrelated to energy, according to Luis Lugo, head of CloudHQ México, cited by Bloomberg Línea. Transmission and distribution works take four to five years, a timeline comparable to installing one's own generation, explained Héctor Sánchez, director of Operations at Equinix. Juan Roberto Lozano, of the National Center for Energy Control (Cenace), noted that timelines of two to five years are also seen in the United States, the United Kingdom and Spain. Cenace has accumulated close to 7 GW of connection requests, and between 1.5 and 2 GW correspond to data centers, according to Expansión.

The first test arrives at the end of 2026, when the industry expects to add 205 MW of supply, and another 205 MW in the first quarter of 2027, according to Energía Estratégica. That infrastructure, which developers build and donate to the CFE, will determine whether the grid keeps pace with the investment.

This article was written with the assistance of artificial intelligence from verified sources and reviewed by a human editor before publication.

This article was drafted with AI assistance from verified sources and reviewed by a human editor before publication.